Team members enter task updates in Project Web App (PWA), and project managers review these updates in PW

You work in the Project Management Office (PMO) for an organization that uses Project Server 2013.
Team members enter task updates in Project Web App (PWA), and project managers review these
updates in PWA.
You discover that team members enter hours worked each day on your project, but they enter
percent complete on another project.
You need to limit the task update method across the enterprise to one method for team members.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose
two.)

You work in the Project Management Office (PMO) for an organization that uses Project Server 2013.
Team members enter task updates in Project Web App (PWA), and project managers review these
updates in PWA.
You discover that team members enter hours worked each day on your project, but they enter
percent complete on another project.
You need to limit the task update method across the enterprise to one method for team members.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose
two.)

A.
Enable the option that indicates resources should report their hours worked every day.

B.
Enable the option to force project managers to use the progress reporting method for all projects.

C.
Ensure that free form is not selected as a tracking method.

D.
Ensure that free form is selected as a tracking method.