The resource manager will be responsible for reporting vendor progress back to the project manager in PW

Your organization uses Project Server 2013. For security reasons, only individuals inside your
organization have access to Project Web App (PWA).
You want to keep track of progress made by a third-party vendor. The vendor will email task
progress to the resource manager. The resource manager will be responsible for reporting vendor
progress back to the project manager in PWA.
You need to enable this functionality.
You add the vendor as a resource in Project Server.
What should you do next?

Your organization uses Project Server 2013. For security reasons, only individuals inside your
organization have access to Project Web App (PWA).
You want to keep track of progress made by a third-party vendor. The vendor will email task
progress to the resource manager. The resource manager will be responsible for reporting vendor
progress back to the project manager in PWA.
You need to enable this functionality.
You add the vendor as a resource in Project Server.
What should you do next?

A.
Assign the resource manager as the Status Manager.

B.
Assign the project manager as the Assignment Owner.

C.
Assign the resource manager as the Assignment Owner.

D.
Assign the administrator as the Status Manager.