You are a project manager who has standard permissions, and your organization uses Project Server
2013.
Some of your resources consistently update their assignments correctly. You want to accept their
future updates without review.
You need to begin accepting their updates without review by using the least amount of effort
possible.
What should you do?
A.
Set up a rule in the Approval Center to automatically accept ail updates, specifying the resources
by name, for all projects.
B.
Set up a VBA macro to automatically accept all updates, specifying the resources by name, for all
projects.
C.
Set up a Project Server 2013 workflow by using Microsoft SharePoint Designer to automatically
accept all updates, specifying the resources by name, for all projects.
D.
Set up a timesheet event handler in the Project Server Settings to automatically accept all
updates, specifying the resources by name, for all projects.