You are a program manager in the Project Management Office (PMO) of an organization that uses
Project Server 2013.
You review your organization’s issue management process.
You need to implement a new issue management process that meets the following requirements:
• All issues for future projects need to be associated with a source.
• Source values are either Internal or External.
What should you do?
A.
Instruct the users to attach a text file with the source information every time they create a new
issue.
B.
Instruct the users to write the information about the source into the description field every time
they create a new issue.
C.
Add a new enterprise custom field named Source with an associated lookup table which contains
the values Internal and External. Make this field required. Save the Project Site as a template for new
Project Sites.
D.
Go to a Project Site, and customize the issue list by including a new column to allow a value from
Internal or External options to be chosen. Make this field required. Save the Project Site as a
template for new Project Sites.