You need to implement a new project creation process which does not affect the projects…

You are a program manager in the Project Management Office (PMO) of an organization that uses
Project Server 2013.
You notice that some projects have been published with incorrect dat
a. You and the project managers spend a lot of time correcting the data problems.
You need to implement a new project creation process which does not affect the projects that are
already created and which allows you to perform the following actions:
• Review the project data after the project managers create the projects.
• Send the projects back to the project managers if you find incorrect data so that they can
make the appropriate corrections.
• Repeat the data verification process unless the data does not have any errors.
• Publish a project only when all of its data is correctly completed.
What should you do?

You are a program manager in the Project Management Office (PMO) of an organization that uses
Project Server 2013.
You notice that some projects have been published with incorrect dat
a. You and the project managers spend a lot of time correcting the data problems.
You need to implement a new project creation process which does not affect the projects that are
already created and which allows you to perform the following actions:
• Review the project data after the project managers create the projects.
• Send the projects back to the project managers if you find incorrect data so that they can
make the appropriate corrections.
• Repeat the data verification process unless the data does not have any errors.
• Publish a project only when all of its data is correctly completed.
What should you do?

A.
Instruct the project managers to include a task named project review every time they create a
project and assign it to you. Project Server will notify you about the project creation. If you find an
error, delete the project, and the project manager should create the project again.

B.
Instruct the project managers to send you an email every time they create a project they need so
that you can review the project. If you find an error, delete the project, and the project manager
should create the project again.

C.
Create a new workflow that automates all of the requirements. Create a new enterprise project
type and link it with the workflow.

D.
Create a Published event handler that automates all of the requirements for this enterprise
project type.



Leave a Reply 1

Your email address will not be published. Required fields are marked *


Main Page

Main Page

Stunning quest there. What occurred after? Thanks!|