You need to include this new field in the Enterprise Gantt Chart in Project Professional 2013…

You are a program manager in the Project Management Office (PMO) of an organization that uses
Project Server 2013. The Enterprise Gantt Chart is visible to all project managers.
You plan to create a new project enterprise custom field to show information about schedule
variance.
You need to include this new field in the Enterprise Gantt Chart in Project Professional 2013 so that
all project managers of actual and future projects who use this view can see this field by default.

What should you do?

You are a program manager in the Project Management Office (PMO) of an organization that uses
Project Server 2013. The Enterprise Gantt Chart is visible to all project managers.
You plan to create a new project enterprise custom field to show information about schedule
variance.
You need to include this new field in the Enterprise Gantt Chart in Project Professional 2013 so that
all project managers of actual and future projects who use this view can see this field by default.

What should you do?

A.
In Project Professional 2013, check-out the Enterprise Global template, modify the Enterprise
Gantt Chart view by adding the new project enterprise custom field, and then update the view.

B.
Create a Project Center view named Enterprise Gantt Chart with the new project enterprise
custom field, and select the Gantt Chart Views format.

C.
Modify the Project Information project details page by adding the new project enterprise custom
field.

D.
In Project Professional 2013, create a blank project, add a new view named Enterprise Gantt
Chart, modify the view by adding the new project enterprise custom field, and then save the view.
Save the project as a template.