You are a project manager in an organization that uses Project Server 2013. You manage two
projects named Proj1 and Proj2.
You create a deliverable dependency between both projects by taking the following actions:
• You create a deliverable named Deliverable1 against a milestone named Milestone1 in Proj1.
The Finish date for Milestone1 and the Deliverable Finish date for Deliverable1 are the same.
• On Proj2, you associate a dependency that has a milestone named Milestone2 to the
Deliverable1.
After several days of work, Proj1 has been rescheduled, which moves the Finish date for Milestone1
ahead by five days.
You need to ensure that these changes are reflected in both projects.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose
two.)
A.
Open Proj1 in Project Professional 2013, open the dependency panel by choosing the Manage
Dependencies option in the Task tab, and select Accept all server changes. Save and publish the
project.
B.
Open Proj2 in Project Professional 2013, select Milestone2, and choose Sync Deliverables option
in the Task tab. Save and publish the project.
C.
Open Proj2 in Project Professional 2013, open the dependency panel by choosing Manage
Dependencies option in the Task tab, and select Accept all server changes. Save and publish the
project.
D.
Open Proj1 in Project Professional 2013, select Milestone1, and choose Sync Deliverables option
in the Task tab. Save and publish the project.
There is an error in the answers transcription.
The right answers would be, in the following order:
Open Proj1 in Project Professional 2013, select Milestone1, and choose Sync Deliverables option
in the Task tab. Save and publish the project. (D)
Open Proj2 in Project Professional 2013, select Milestone2, and choose Sync DEPENDENCIES option
in the Task tab. Save and publish the project (B)