You are a project manager for an organization that uses Project Server 2013.
Only administrators have Project Professional 2013. You use Project Web App (PWA) for schedule
management.
You modify your schedule after some changes are approved through your organization’s Project
Scope Change process.
You need to set a baseline for the project.
What should you do?
A.
Ask the administrator to access the project schedule in PWA, select the tasks affected by the
change request, and baseline those tasks.
B.
Open the project schedule in PWA, select the tasks affected by the change request, and baseline
those tasks.
C.
Open the project schedule in PWA and set the baseline from the option in the ribbon.
D.
Ask the administrator to set the baseline because a baseline can only be set in Project
Professional 2013.