you need to reserve proposed demand for the final 12 months

You are a project manager who uses Project Online. Your project is scheduled to run for at least 18
months. You create a schedule for the first six months, including estimated resource demand, using
Project Professional 2013.
For planning purposes, you need to reserve proposed demand for the final 12 months.
What should you do?

You are a project manager who uses Project Online. Your project is scheduled to run for at least 18
months. You create a schedule for the first six months, including estimated resource demand, using
Project Professional 2013.
For planning purposes, you need to reserve proposed demand for the final 12 months.
What should you do?

A.
Create new tasks in the project to represent the unplanned portion of the project. Assign
resources to these tasks and set their booking type to committed.

B.
Create a resource plan and enter the resource requirements for the final 12 months.

C.
Create a resource plan and set the Resource Utilization to calculate from the project until a date
six months from now.

D.
Create new tasks in the project to represent the unplanned portion of the project. Assign
resources to these tasks and set their booking type to proposed.

Explanation:



Leave a Reply 1

Your email address will not be published. Required fields are marked *


jc

jc

I think it is B