You are a project manager for an organization that uses Project Online.
You create a resource plan to provide high level resource demand during the portfolio intake and
selection process.
Your project is now selected for detailed planning. You complete a detailed work breakdown
structure (WBS).
You need to remove the resource demand from the resource plan.
What should you do?
A.
Change the Calculate From setting on the resource plan.
B.
Go to Project Center and delete the resource plan.
C.
Inactivate the resource plan.
D.
Go to Server Settings and delete the resource plan.
E.
Set the Publish flag to No on the resource plan.