You need to configure your resources to enable this method of assigning tasks

You are a project manager who uses Project Server 2013 and Project Professional 2013. You build a
project with common tasks for which many resources on your team can be used.
Because your resources have responsibilities outside of the project, you would like to have them
assign themselves to tasks they are able to complete.
You need to configure your resources to enable this method of assigning tasks.
What should you do?

You are a project manager who uses Project Server 2013 and Project Professional 2013. You build a
project with common tasks for which many resources on your team can be used.
Because your resources have responsibilities outside of the project, you would like to have them
assign themselves to tasks they are able to complete.
You need to configure your resources to enable this method of assigning tasks.
What should you do?

A.
Open the Build Team From Enterprise dialog box for the project and change each resource on the
team to Proposed. Assign the resources. Then have them view their tasks in the My Tasks view and
submit changes to the project manager.

B.
Create your project in Project Professional 2013 and publish the file without any resources
assigned. Inform your team to review the tasks in the Project Web App (PWA) and email you which
tasks they are able to work on.

C.
Create your project in Project Professional 2013 and then email it to each resource, asking them
to add their name to the Resource Field column for each task they feel they could complete.

D.
Create a Generic Work resource and assign it to the same team as the other resources. Check the
Team Assignment Pool checkbox and assign this resource to the tasks in your project file. Have your
resources add team tasks to their My Tasks views for the project and submit for reassignment to the
task they are able to work on.



Leave a Reply 0

Your email address will not be published. Required fields are marked *