You are a project manager who uses Project Server 2013 and Project Professional 2013.
You are managing a project that has already begun. A new change request has been pre-approved,
and the director wants to understand the impact to the overall project schedule prior to formally
approving the project to include in the project schedule.
You add the change request to your project schedule. Your original baseline is Baseline1.
You need to include the change request in your baseline to see the impact of your overall project
schedule including duration, work, and cost.
What should you do?
A.
Set Interim plan for the entire project.
B.
Set Baseline1 for the selected tasks.
C.
Set Interim plan for the selected tasks.
D.
Set Baseline1 for the entire project.