You work in an organization that uses Project Online. Project managers have full control over
resource assignments.
You work in the Project Management Office (PMO) and discover that two of your critical resources
are overallocated in the Resource Center for future work. They are critical resources because they
have specialized skills that no one else in your organization has, and they are integral to several
projects.
You need to determine how to correct the overallocation of these resources.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose
two.)
A.
Manage resource plan task assignments.
B.
Manage Project assignments.
C.
Manage Microsoft SharePoint task assignments.
D.
Manage Project issue assignments.