You need to load your project with your desired resources against tasks

You are a project manager who uses Project Server 2013.
You build a project plan with the required tasks and want to add your resources. You know which
resources you would like to include but are not sure if they will be approved for your project.
You cannot formally assign these resources to the project until it is approved.
You need to load your project with your desired resources against tasks.
What should you do?

You are a project manager who uses Project Server 2013.
You build a project plan with the required tasks and want to add your resources. You know which
resources you would like to include but are not sure if they will be approved for your project.
You cannot formally assign these resources to the project until it is approved.
You need to load your project with your desired resources against tasks.
What should you do?

A.
Create your project in Project Professional 2013 and add your desired resources by name locally
until they are approved for use.

B.
Create your project in Project Web App (PWA) and build the team from the enterprise. When
adding resources, specify the booking type to proposed and add them to your tasks.

C.
Ask the administrator to create a custom field for you to acknowledge the commitment type of
your resource.

D.
Have the administrator create an alternate resource for your resources and use those to allocate
your resource needs.