What are two possible ways to achieve this goal?

You are a project manager for an organization that uses Project Server 2013. One enterprise project
has grown in complexity and size; the project manager creates sub-sites to organize the work by
team.
All the teams are comfortable working with a familiar tool, such as the Microsoft SharePoint site.
However, management cannot view all of the work being performed in the portfolio, and they need
to permanently make decisions about the best use of the resources.
You need to bring all of this work into visibility in the least amount of time and without affecting
current resource processes. What are two possible ways to achieve this goal? (Each correct answer
presents a complete solution. Choose two.)

You are a project manager for an organization that uses Project Server 2013. One enterprise project
has grown in complexity and size; the project manager creates sub-sites to organize the work by
team.
All the teams are comfortable working with a familiar tool, such as the Microsoft SharePoint site.
However, management cannot view all of the work being performed in the portfolio, and they need
to permanently make decisions about the best use of the resources.
You need to bring all of this work into visibility in the least amount of time and without affecting
current resource processes. What are two possible ways to achieve this goal? (Each correct answer
presents a complete solution. Choose two.)

A.
Add the SharePoint Sites to Project Web App from the Project Center.

B.
Start an import process from Project Professional and then publish those projects in Project Web
App (PWA).

C.
Use the Get Started with Project Web App to add the existing SharePoint sites to Project Web App
(PWA).

D.
Use the Get Started with Project Web App to create new enterprise projects with the same
information.