Your organization is in the process of deploying Project Server 2013.
Your business unit manages projects with different tools, such as Microsoft Excel and different
versions of Project Professional and Standard. Your business unit needs to upload and manage the
projects in the new platform.
You need to guarantee that the projects are uploaded in an efficient way while maintaining data
integrity. Which two actions should you perform? (Each correct answer presents part of the solution.
Choose two.)
A.
Import the projects from Excel spreadsheets to Project Professional 2013 by copying and pasting
the information in the correct fields. Then publish to Project Web App (PWA).
B.
Use Project Professional 2013 connected to Project Server 2013, open the standalone project
plan, click Save As, and publish the plan to Project Server.
C.
Import the projects from Project Standard 2013 to Project Web App (PWA) with the Import
Wizard in order to map any local resources to enterprise resources.
D.
Use Project Professional 2013 connected to Project Server 2013, open the Excel file in Project
Professional 2013, run the import wizard, and save and publish the plan to Project Server.