Your organization is using Project Online to facilitate the selection of optimal portfolios.
The Project Management Office (PMO) expects to analyze the portfolio of projects in a short period
of time by using the efficient frontier and the strategic value provided by the tool.
You need to ensure the tool provides the expected outcome.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose
three.)
A.
Create a custom workflow that allows the capture of projects with business-relevant information.
B.
Define the list of projects that include cost estimates.
C.
Create a custom field to be used as alias when force-in or force-out options are selected.
D.
Create a custom cost field to be used as a cost constraint.
E.
Define and rank specific business drivers or other factors relevant to the project approval process.
F.
Populate and configure the resource pool, including maximum units, resource calendars, and a
primary role field.
Explanation: