You are a program manager for an organization that uses Project Server 2013.
You work in a master project, which contains ten sub-projects. One of your project managers makes
changes to a sub-project and publishes it.
You open the master project and realize that these changes are not reflected in the master project
schedule.
You need to ensure these changes are reflected in the master project.
What should you do?
A.
Open the master project in Project Web App (PWA), click on the Calculate Project to calculate all
changes, and then publish.
B.
Open the master project in Project Professional 2013, click on the Calculate Project to calculate all
changes, and then publish.
C.
Open the master project in Project Professional 2013, expand all sub-projects, and then publish.
D.
Open the master project in Project Web App (PWA), expand all sub-projects, and then publish.