You need to ensure that the previously accepted status updates are visible in PW

You are a project manager for a company that uses Project Server 2013 in Project Server Permission
Mode.
You have been managing a project for several months. You go on vacation, and you delegate your
project management responsibility to one of your coworkers.
Your coworker accepts multiple status updates on the project. When you return, you notice that no
project updates are visible in Project Web App (PWA), and there are no status updates awaiting
approval.
You need to ensure that the previously accepted status updates are visible in PWA.
What should you do?

You are a project manager for a company that uses Project Server 2013 in Project Server Permission
Mode.
You have been managing a project for several months. You go on vacation, and you delegate your
project management responsibility to one of your coworkers.
Your coworker accepts multiple status updates on the project. When you return, you notice that no
project updates are visible in Project Web App (PWA), and there are no status updates awaiting
approval.
You need to ensure that the previously accepted status updates are visible in PWA.
What should you do?

A.
Set the date range in the Approval’s page to include last week’s updates.

B.
Have your team resubmit last week’s status updates.

C.
Have your team resubmit last week’s timesheet updates.

D.
Publish the task updates from the Status History page.