You need to create a relationship between both projects that meets the following requirements: • Milestone2 depends on Milestone1

You are managing two projects named Proj1 and Proj2. Proj1 has a milestone named Milestone!.
Proj2 has a milestone named Milestone2.

You need to create a relationship between both projects that meets the following requirements:
• Milestone2 depends on Milestone1.
• The relationship provides visibility without affecting Milestone2’s schedule.
What should you do?

You are managing two projects named Proj1 and Proj2. Proj1 has a milestone named Milestone!.
Proj2 has a milestone named Milestone2.

You need to create a relationship between both projects that meets the following requirements:
• Milestone2 depends on Milestone1.
• The relationship provides visibility without affecting Milestone2’s schedule.
What should you do?

A.
Open Project Professional 2013 and create a master project with Proj1 and Proj2 as subprojects.
Make Milestone2 a predecessor of Milestone1. Save and publish the master project.

B.
Open Project Professional 2013 and create a master project with Proj1 and Proj2 as subprojects.
Make Milestone1 predecessor of Milestone2. Save and publish the master project.

C.
Open Proj1 in Project Professional 2013 and create a deliverable for Milestone1. Save and publish
Proj1. Open Proj2 in Project Professional 2013, add a new dependency for the deliverable on Proj1,
and link the dependency to Milestone2. Save and publish Proj2.

D.
Open Proj2 in Project Professional 2013 and create a deliverable for Milestone2. Save and publish
Proj2. Open Proj1 in Project Professional 2013, add a new dependency for the deliverable on Proj2,
and link the dependency to Milestone1. Save and publish Proj1.