You are a program manager in the Project Management Office (PMO) of an organization that is
implementing Project Server 2013.
You plan to include five of your organization’s departments in the first rollout of Project Server 2013.
You need to develop a project creation process that meets the following requirements:
• Each department must have its own Project Site template.
• Each department must have its own Project Schedule template.
• The project creation process needs to be developed in the least amount of time.
What should you do?
A.
Create five projects, one for each department. Send the project file via email to the respective
department leader. Instruct them to use the project file as a template every time they need to
create a new project.
B.
Create five Microsoft SharePoint sites and five projects, one for each department. Publish the
projects into the respective SharePoint site. Instruct the department leads to create a copy of their
SharePoint site and to use the project file as a template each time they need to create a new project.
C.
For each department, create one enterprise project template (EPT), one Project Site template, and
one project template. Associate the Project Site template and the project template with the EPT.
D.
Create a single Microsoft SharePoint site and one project for each department, and then publish
the projects into the SharePoint site. Instruct the department leads to create a new sub-site from
the SharePoint site and to use the appropriate project file as the template each time they need to
create a new project.