Ensure that the Inspect Ski Lifts task must be completed before the Groom Slopes task can begin




Ensure that the Inspect Ski Lifts task must be completed before the Groom Slopes task can begin.




Ensure that the Inspect Ski Lifts task must be completed before the Groom Slopes task can begin.

Answer: See the explanation.

Explanation:
Step 1: Click Tasks
Step 2: Locate the select the Groom Slopes task.

Step 3: Click the Edit Item button.
Step 4: Set the Predecessors field to: Inspect Ski Lifts.
Note: You use a Gantt chart in project management as a way to visually show the sequence of tasks
in a project along a horizontal timeline.