Which of the following recovery plan test results would…

Which of the following recovery plan test results would be most useful to management?

Which of the following recovery plan test results would be most useful to management?

A.
elapsed time to perform various activities.

B.
list of successful and unsuccessful activities.

C.
amount of work completed.

D.
description of each activity.

Explanation:
The team of testers must agree upon what activities are getting tested and how to properly determine success
or failure.
Incorrect Answers:
A: The key when testing the recovery plan is to know fail or success of the activities, not the elapsed time of
them.
C: The recovery plan test refers to activities not to work completed.
D: The key when testing the recovery plan is to know fail or success of the activities, not the description time of
time.

Harris, Shon, All In One CISSP Exam Guide, 6th Edition, McGraw-Hill, 2013, p. 954