What does a checklist burnup chart display?
A.
The estimated remaining hours of work for the sprint
B.
The count of items completed and whether the team will complete the remaining items by
the end of the sprint
C.
The actual remaining hours of work for the sprint
D.
The count of items remaining and whether the team will complete the remaining items by
the end of the sprint