You and your project team are identifying the risks that may exist within your project. Some of the risks are small risks that won’t affect your project much if they happen. What should you do with these identified risk events?
A.
These risks can be accepted.
B.
These risks can be added to a low priority risk watch list.
C.
All risks must have a valid, documented risk response.
D.
These risks can be dismissed.