You work as a purchasing manager at ABC.com. The company has recently implemented a
Microsoft Dynamics AX 2012 ERP system.
You have not configured any custom workflows for purchase requisitions.
A user named Kim works in the purchasing department. Kim uses the web portal to submit a
purchase requisition. You plan to approve the purchase requisition.
Which of the following statements is true?
A.
After approving the purchase requisition, you will need to manually create a purchase order.
B.
After approving the purchase requisition, a purchase order is automatically created for further
processing.
C.
After approving the purchase requisition, a purchase order is automatically sent to the supplier.
D.
A purchase order needs to be raised before the purchase requisition can be approved.
Explanation: