Thomas is the project manager of the NHJ Project for his company. He has identified several positive risk events within his project and he thinks these events can save the project time and money. Positive risk events, such as these within the NHJ Project are also known as what?
A.
Opportunities
B.
Benefits
C.
Ancillary constituent components
D.
Contingency risks