You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of
$945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent
$455,897 to reach the 45 percent complete milestone.
What is the project’s schedule performance index?
A.
1.06
B.
0.93
C.
-$37,800
D.
0.92