What approach can a project manager use to improve the …

What approach can a project manager use to improve the project’s performance during qualitative risk analysis?

What approach can a project manager use to improve the project’s performance during qualitative risk analysis?

A.
Create a risk breakdown structure and delegate the risk analysis to the appropriate project team members.

B.
Focus on high-priority risks.

C.
Focus on near-term risks first.

D.
Analyze as many risks as possible regardless of who initiated the risk event.