Which one of the following is a valid risk response for…

There are seven risk responses for any project. Which one of the following is a valid risk response for a negative risk event?

There are seven risk responses for any project. Which one of the following is a valid risk response for a negative risk event?

A.
Enhance

B.
Exploit

C.
Acceptance

D.
Share