You work as a project manager for TechSoft Inc. You, the project team, and the key project stakeholders have completed a round of quantitative risk analysis. You now need to update the risk register with your findings so that you can communicate the risk results to the project stakeholders – including management. You will need to update all of the following information except for which one?
A.
Probability of achieving cost and time objectives
B.
Risk distributions within the project schedule
C.
Probabilistic analysis of the project
D.
Trends in quantitative risk analysis