You and your project team have identified the project risks and now are analyzing the probability and impact of the risks. What type of analysis of the risks provides a quick and high-level review of each identified risk event?
A.
Qualitative risk analysis
B.
Seven risk responses
C.
Quantitative risk analysis
D.
A risk probability-impact matrix