You are the project manager of QSL project for your organization. You are working you’re your project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique are you using as a part of the risk identification process?
A.
Cause and effect diagrams
B.
System or process flowcharts
C.
Predecessor and successor diagramming
D.
Influence diagrams