Your primary SmartCenter Server is installed on a SecurePlatform Pro machine, which is also a VPN-1 Pro Gateway. You want to implement Management High Availability (HA). You have a spare machine to configure as the secondary SmartCenter Server. How do you configure the new machine to be the standby SmartCenter Server, without making any changes to the existing primary SmartCenter Server? (Changes can include uninstalling and reinstalling.)
A.
You cannot configure Management HA, when either the primary or secondary SmartCenter Server is running on a VPN-1 Pro Gateway.
B.
The new machine cannot be installed as the Internal Certificate Authority on its own.
C.
The secondary Server cannot be installed on a SecurePlatform Pro machine alone.
D.
Install the secondary Server on the spare machine. Add the new machine to the same network as the primary Server.