what are the top four risks that are associated with poor change management process and procedures?

According to ITIL® v3 framework, what are the top four risks that are associated with poor change
management process and procedures?

According to ITIL® v3 framework, what are the top four risks that are associated with poor change
management process and procedures?

A.
Authorized changes, low change success, high emergency changes, planned outages

B.
High change success, high emergency changes, planned outages, unauthorized changes

C.
High change success, low emergency changes, unauthorized changes, unplanned outages

D.
Low change success, high emergency changes, unauthorized changes, unplanned outages