Which three pieces of information should be documented for each step of each phase in a design implementation plan? (Choose three.)
A.
easy guidelines in case of failure
B.
estimated rollback time in case of failure
C.
simple implementation guidelines
D.
estimated implementation time
E.
design document references
F.
step description
Explanation:
The implementation of a network consists of several phases. The each step should contain the following information:
Cisco Press CCDA 640-864 Official Certification Guide Fourth Edition, Chapter 1
There is a VCE that gives the answer as “easy guidelines in case of failure” instead of estimated implementation time. Which is the correct one?
CCDA 640-864 Official Cert Guide Chapter 1 Page 14 states, “Each step in the implementation should includes a description, detailed implementation guidelines, estimated time to implement, rollback steps in case of a failure, and any additional reference information.”
This means that A and C should also be included as the correct answer. May be question should say, “choose all that apply”.
Easy and Simple (A and C) are not part of that description. Rollback steps are required but not roll back time. I think D and E are definitely correct, then probably F; or possibly B.