What is one key objective of the operations readiness assessment performed in the plan phase?
A.
align business requirements with technical requirements
B.
install and test system components in a non-production environment
C.
evaluate the readiness of a customer’s current operations and network management infrastructure to support a new technology
D.
create a plan to recycle used equipment
Explanation:
Cisco Lifecycle Services:
During the plan phase of the Cisco Lifecycle Services approach, the project team needs to assess the current network, site, and operations readiness, which will aid in the design of the proposed technologies. In addition, the project team needs to plan for project management resources, as well as assess security vulnerability of the current system. technologies. In addition, the project team needs to plan for project management resources, as well as assess security vulnerability of the current system.