Which two statements correctly describe the relationship among the Scheduler components: job,
program, and schedule? (Choose two)
A.
A job is specified as part of a program definition
B.
A program can be used in the definition of multiple jobs
C.
A program and job can be specified as part of a schedule definition
D.
A program and schedule can be specified as part of a job definition
Explanation:
http://docs.oracle.com/cd/B19306_01/server.102/b14231/schedover.htm (Topic: How
Programs, Jobs and Schedules are Related)
Topic 2, Pool 2
Correct answers: B,D
I agree with you.
First of all there are expected 2 correct answers. And another things that A is not correct anyhow.
http://docs.oracle.com/cd/E11882_01/server.112/e25494/scheduse.htm
Take a look at the description of the view DBA_SCHEDULER_JOBS.
You will see that a program and a schedule can be associated with a JOB.
That is, B and D are corrects.
I agree with you
I agree with B,D.
Guys might want to check
http://www.aiotestking.com/oracle/which-two-statements-correctly-describe-the-relationship-among-the-scheduler-components-job-program-and-schedule-2/