After having the kick-off meeting for a new site survey project with your customer, which three
factors need to be considered prior to beginning a WLAN site survey? (Choose three.)
A.
Will an additional trip to the facility to perform the initial walkthrough be required?
B.
How much time should be allocated to survey the locations for the controllers?
C.
Will any additional regulatory or safety training be required to complete the site survey?
D.
Is access available to all areas of the customer facility where the WLAN is planned to be
deployed?
E.
Which types of controllers and switches will be required to fully conduct the site survey in all
areas of the customer facility?
F.
Is access available to customer employees so that initial interviews can be performed?
Explanation: