Refer to the exhibit. CCNP.com is planning to implement load balancing for traffic between
hosts on the 172.16.10.0/24 and 172.16.20./24 networks. You have been asked to review
the implementation plan for this project.
Which statement about the plan is true? Select the best response.
Implementation Plan
1. Configure variance on R1 and R4.
2. Use traceroute to validate load balancing has
been activated.
3. Document configuration changes.
A.
It is complete as written.
B.
It should include a task to configure EIGRP multipath equal to 2 on R1 and R4.
C.
It should include a task to implement OSPF because it handles unequal cost load
balancing most efficiently using variance.
D.
It should include a task that establishes a baseline before and after the configuration has
been changed.
Explanation:
A complete implementation plan should be:
1. Configure variance on R1 and R4
2. Use traceroute to validate load balancing has been activated
3. Document configuration changes
4. Establish a new traffic throughput baseline
5. Compare the new and old baselines and verify that load balancing is implemented as
desired.