Which statement about the plan is true?

Refer to the exhibit. CCNP.com is planning to implement a new secure OSPF network to
support traffic between clients on the 172.16.10.0/24 network and the file server on the
172.16.20./24 network. You have been asked to review the implementation plan for the
OSPF project.
Which statement about the plan is true?

Refer to the exhibit. CCNP.com is planning to implement a new secure OSPF network to
support traffic between clients on the 172.16.10.0/24 network and the file server on the
172.16.20./24 network. You have been asked to review the implementation plan for the
OSPF project.
Which statement about the plan is true?

A.
It is complete as written.

B.
It should include a task that shuts down all unusedinterfaces.

C.
It should include tasks that enable and verify OSPFauthentication.

D.
It should include a task that establishes a file transfer baseline before and after the
configuration is changed.

Explanation:
The complete implementation plan should be
1. Enable OSPF process 1 on all routers
2. Enable area 0 on R2, R3 and R4
3. Enable area 10 on R1, R2 and R3
4. Enable area 20 on R4 and R5
5. Enable and verify OSPF authentication
6. Verify that all routers contain a complete routing table
7. Verify that the clients can successfully access the server
8. Document configuration changes