ROUTE.com is planning to implement EIGRP load balancing for traffic between hosts on the
172.16.10.0/24 and 172.16.20./24 networks. You have been asked to review the implementation
plan for this project. Which statement about the plan is true?
A.
It is complete as written.
B.
It should include a task to configure multipath to equal a value of 2 on R1 and R4.
C.
It should use a ping instead of a traceroute to validate that load balancing has been activated.
D.
It should contain a task that documents the changes made to the configurations.
Explanation:
This implementation plan is complete because it has all the requirements for an EIGRP load
balancing process.
I think D is the better answer here.