ROUTE.com is planning to implement load balancing for traffic between hosts on the
172.16.10.0/24 and 172.16.20./24 networks. You have been asked to review the implementation
plan for this project. Which statement about the plan is true?
A.
It is complete as written.
B.
It should include a task to configure EIGRP multipath equal to 2 on R1 and R4.
C.
It should include a task to implement OSPF because it handles unequal cost load balancing
most efficiently using variance.
D.
It should include a task that establishes a baseline before and after the configuration has been
changed.