Data Center floor loading under a rack is dependent on which two factors?

Data Center floor loading under a rack is dependent on which two factors?

(Choose two)

Data Center floor loading under a rack is dependent on which two factors?

(Choose two)

A.
Rack weight

B.
Equipment being installed

C.
Square footage

D.
CFM volume in the Data Center

Explanation:
According to the DCUCD training material, page 1-10:

Floor loading:
– Affected by rack weigth
– Depends on the equipment installed into the rack