When you migrate a mission-critical application, which method requires the least amount of downtime and data loss?

When you migrate a mission-critical application, which method requires the least amount of downtime and data loss?

When you migrate a mission-critical application, which method requires the least amount of downtime and data loss?

A.
overnight migration; cold conversion

B.
overnight migration; hot conversion

C.
gradual migration; cold conversion

D.
gradual migration; hot conversion

Explanation:
24