During the plan phase, which template is used during the assess and document infrastructure requirements for the proposed solution task?
A.
IPC Project Plan
B.
Operational Assessment Checklist
C.
Vertical Industry Snapshots
D.
Site Requirements Specification Document
E.
Staging Plan