Within the prepare phase, which two tasks are required to begin the prepare for business requirements workshop activity? (Choose two.)
A.
Document User-Level Functionality Requirements
B.
Document Vertical Business Initiatives Requirements
C.
Identify key stakeholders for the Business Requirements Development Workshop
D.
Conduct a Solution Value Assessment
E.
Send Invitations
F.
Document Corporate Business Initiatives Requirements
Explanation:
Sending invitations” is a part of the “Prepare the Business Requirements Workshop” and “Conduct the Solution Value Assessment” is a part of the “Conducting the Business Requirements Workshop” task, not of his preparation.