Low level design, site readiness report, project management plan, network implementation plan, and systems acceptance test plan are pre-requisites for which service component in the design phase?
A.
Migration Plan Development
B.
Project Kick-off
C.
Business Plan
D.
Staff Plan Development
E.
Staging Plan
F.
Implementation Kick-off Meeting