which of the following customer benefits?

Conducting a project kick-off in the plan phase provides which of the following customer benefits?

Conducting a project kick-off in the plan phase provides which of the following customer benefits?

A.
reduce the risk of downtime due to facilities-related problems

B.
confirm project roles and responsibilities, as well as milestone dates

C.
ensure that it receives detailed network diagrams

D.
ensure end-user support immediately after the launch of a new system