In the Development Project Management Service component within the plan phase, which activity is associated with the task of proposing and gaining agreement on a governance model that will be used to communicate to key stakeholder and business owners?
A.
Develop the work breakdown structure
B.
Develop a project management plan
C.
Produce a master project plan
D.
Perform project control and monitoring
E.
Conduct project kickoff workshops